(Created page with "Activity Insert brief abstract of the activity to be assessed here [edit] Hazard identification Consider the hazards involved in conducting this activity and list each hazard...")
 
(Final assessment of risk)
 
(9 intermediate revisions by one user not shown)
Line 1: Line 1:
Activity
+
= Risk assessment form for Vacuum Former =
  
Insert brief abstract of the activity to be assessed here
+
[[Equipment|Equipment]] / [[Equipment/VacuumFormer|Vacuum Former]]
  
[edit] Hazard identification
+
===Activity===
 +
Vacuum forming plastic material
  
Consider the hazards involved in conducting this activity and list each hazard  
+
===Hazard identification===
Hazard 1
+
''Consider the hazards involved in conducting this activity and list each hazard''
Hazard 2
+
Hazard 3
+
  
[edit] Persons at risk
+
1. Fire
  
Consider who might be put at risk by the hazards listed above
+
2. Burns
Persons
+
Persons
+
Persons
+
  
[edit] Initial assessment of risk
+
3. Electric Shock
  
 +
===Persons at risk===
 +
''Consider who might be put at risk by the hazards listed above''
 +
* The user is subject to 1, 2 and 3.
 +
* The space and all occupants are subject to 1.
  
Hazard identified  
+
===Initial assessment of risk===
 +
{| class="wikitable"
 +
|-
 +
!|Hazard identified
 +
!|Severity
 +
!|Probability
 +
!|Risk Factor (Severity x probability)
 +
|-
 +
|Fire
 +
|5
 +
|2
 +
|10
 +
|-
 +
|Burns
 +
|3
 +
|3
 +
|9
 +
|-
 +
|Electric Shock
 +
|3
 +
|2
 +
|6
 +
|}
  
Severity
+
Categorising the risk level as 1-4(Low), 5-9(Moderate), 10-15(High) or 16-25 (Unacceptable) shows that the potential level of risk in this activity is '''High'''. 
 +
Further measures are '''needed/not needed''' to reduce the risk to an acceptable level.
  
Probability
+
===Control measures===
 
+
* Necessary control measures arising from the hazard identified of '''Fire''' are:
Risk Factor
+
** Don't leave the machine running unattended.
 
+
** Do not overheat the plastic material.
Hazard 1  1~5  1~5  Severity x probability 
+
* Necessary control measures arising from the hazard identified of '''Burns''' are:
Hazard 2  1~5  1~5  Severity x probability 
+
** Always use handles, do not touch the hood.
Hazard 3  1~5  1~5  Severity x probability 
+
** Always wait a couple of minutes before touching the plastic.
 
+
** Never put your hand between the plastic and the heater elements.
Categorising the risk level as 1-4(Low), 5-9(Moderate), 10-15(High) or 16-25 (Unacceptable) shows that the potential level of risk in this activity is ########. Further measures are needed/not needed to reduce the risk to an acceptable level.
+
* Necessary control measures arising from the hazard identified of '''Electric Shock''' are:
 
+
** Carry out a visual check and check the test date before use.
[edit] Control measures
+
Necessary control measures arising from the hazard identified of ####### are:  
+
Necessary control measures arising from the hazard identified of ####### are:  
+
Necessary control measures arising from the hazard identified of ####### are:  
+
 
+
[edit] Final assessment of risk
+
  
 +
===Final assessment of risk===
 
The assessed risk taking into account the implementation of the control measures listed, and adherence to the SSOW (Safe System of Work) if applicable is as follows:  
 
The assessed risk taking into account the implementation of the control measures listed, and adherence to the SSOW (Safe System of Work) if applicable is as follows:  
  
 +
{| class="wikitable"
 +
|-
 +
!|Hazard identified
 +
!|Severity
 +
!|Probability
 +
!|Risk Factor
 +
|-
 +
|Fire
 +
|1
 +
|1
 +
|1 (Low)
 +
|-
 +
|Burns
 +
|1
 +
|1
 +
|1 (Low)
 +
|-
 +
|Electric Shock
 +
|3
 +
|1
 +
|4 (Low)
 +
|}
  
Hazard identified
+
''When completing Risk Assessment please consider the if First Aid assistance might be appropriate if the calculated Risk level (Severity x Probability) is greater than 5''
  
Severity
+
The risk now falls into the category '''LOW''' and is considered to be acceptable.
 
+
Probability
+
 
+
Risk Factor
+
 
+
Hazard 1  1~5  1~5  Severity x probability 
+
Hazard 2  1~5  1~5  Severity x probability 
+
Hazard 3  1~5  1~5  Severity x probability 
+
 
+
When completing Risk Assessment please consider the if First Aid assistance might be appropriate if the calculated Risk level (Severity x Probability) is greater than 5
+
 
+
The risk now falls into the category ####### and is considered to be acceptable.  
+
  
 
Authorised by  
 
Authorised by  
 +
 +
Sign:
  
Sign:
+
Print:
 
+
Print:  
+
  
 
Date:
 
Date:

Latest revision as of 20:27, 26 July 2013

Risk assessment form for Vacuum Former

Equipment / Vacuum Former

Activity

Vacuum forming plastic material

Hazard identification

Consider the hazards involved in conducting this activity and list each hazard

1. Fire

2. Burns

3. Electric Shock

Persons at risk

Consider who might be put at risk by the hazards listed above

  • The user is subject to 1, 2 and 3.
  • The space and all occupants are subject to 1.

Initial assessment of risk

Hazard identified Severity Probability Risk Factor (Severity x probability)
Fire 5 2 10
Burns 3 3 9
Electric Shock 3 2 6

Categorising the risk level as 1-4(Low), 5-9(Moderate), 10-15(High) or 16-25 (Unacceptable) shows that the potential level of risk in this activity is High. Further measures are needed/not needed to reduce the risk to an acceptable level.

Control measures

  • Necessary control measures arising from the hazard identified of Fire are:
    • Don't leave the machine running unattended.
    • Do not overheat the plastic material.
  • Necessary control measures arising from the hazard identified of Burns are:
    • Always use handles, do not touch the hood.
    • Always wait a couple of minutes before touching the plastic.
    • Never put your hand between the plastic and the heater elements.
  • Necessary control measures arising from the hazard identified of Electric Shock are:
    • Carry out a visual check and check the test date before use.

Final assessment of risk

The assessed risk taking into account the implementation of the control measures listed, and adherence to the SSOW (Safe System of Work) if applicable is as follows:

Hazard identified Severity Probability Risk Factor
Fire 1 1 1 (Low)
Burns 1 1 1 (Low)
Electric Shock 3 1 4 (Low)

When completing Risk Assessment please consider the if First Aid assistance might be appropriate if the calculated Risk level (Severity x Probability) is greater than 5

The risk now falls into the category LOW and is considered to be acceptable.

Authorised by

Sign:

Print:

Date: